- Follow up with land vendor En. Hailuddin, all the drawing still pending at Silk Highway. He will follow up with Silk, and arrange a meeting with us after obtain the drawing from Silk.
- Follow up with AIRIS Cik Hidayah regards the IWK status. We request IWK drawing from them, then will pass to Royal, Sam to follow up with IWK.
- Request Hidayah to send over the amount to paid for JPS.
PSS Bukit Kajang Toll
Wednesday, May 18, 2011
Follow up with Land Vendor
18 May 2011
Follow up with Land Vendor
09 May 2011
- Follow up with lander vendor regards the drawing status at Silk Highway, they said there is no respond yet from Silk after submission.
Project Coordination Meeting 01
28 April 2011
- PDB requested SARBA to submit BG before start work.
- AIRIS reported the Majlis approval status.
- IWK requested pump system, they rejected septic tank. AIRIS had appeal twice, but still rejected.
- JPS, targeted approval on 01 Jun 2011. AIRIS confirm there is no OSD.
- KM and BP drawing had pass to land vendor (RainKall), pending land vendor submit to Silk highway.
- SARBA had highlighted, full direct access approval yet to release, only conceptual approval obtained. SARBA requested to revised the project contract start date (which is date after obtained full direct access approval).
- PDB had asking SARBA arrange meeting with land vendor and road consultant to clarify to work scope
- Low HE had send out an email to PDB after discussion with land vendor. Land vendor will confirm back the date for meeting.
Kick Off Meeting
4 April 2011
- It is to remind that the consultant fee is 10% including MPKJ ans SKPL.
- PDB informed that direct access approval obtain, but no copy to SARBA.
- KM and BP still yet to submit. AIRIS will submit ASAP. Both KM and BP can submit concurrently.
- All external department approval granted, except IWK. IWK requested a pump system
- AIRIS contact: Cik Hidayah, 017-3036475
- SILK contact: En. Rasid bin Daun, 03-89210000